Retrofitting of ESPs for H.P. Boiler Units # 5&6 (2X150 TPH)
Rourkela, Odisha
SAIL
Completed
Design, Manufacture, Supply, Erection, Commissioning & PG Test of ESP
Post Retrofit /R & M Benefits
Emission levels remarkably brought down from the existing level.
Replacement of all the internals and all the TR sets with the state of the art EPIC III Controllers.
Life extension of the ESP.